About the data
MixedDemo date Nov 9, 2026
Real sources
15 sources| Source | Used for | Retrieved | Data |
|---|---|---|---|
| ADF&G Anadromous Waters Catalog 2026, anadromous streams layer | 1,400 stream lines in nine areas (Kachemak Bay, Lake Creek and Yentna, Chatanika, Juneau, Ketchikan, Kodiak, Valdez, Sitka, Kenai): Fish Habitat screening and site maps | Nov 10, 2026 | Real public data |
| ADF&G Habitat Section regional boundaries | Habitat office phone and email on the home page | Nov 10, 2026 | Real public data |
| DNR OpenData Land Permit or Lease polygons | Existing LAS cases checked at intake and drawn on site maps (cached in ak-las) | Nov 8, 2026 | Real public data |
| DNR OpenData Easement polygons | Existing LAS easement cases at intake (cached in ak-las) | Nov 8, 2026 | Real public data |
| DMLW land use permit process, fees, offices | 30-day permit aim, fees, land office addresses and phones | Nov 8, 2026 | Real public data |
| DMLW Lands Section | Lease 9 to 12 months, easement 6 to 8 months | Nov 10, 2026 | Real public data |
| AO 355 final report | Land use permit 14-day public notice | Nov 10, 2026 | Real public data |
| Administrative Order 360 | Public status and timelines direction | Nov 10, 2026 | Real public data |
| Alaska Statutes and Administrative Code (akleg.gov) | Every legal clock, notice period and citation on a step | Nov 10, 2026 | Real public data |
| ADF&G Habitat permit FAQ | Fish Habitat and Special Area 2 to 4 week target | Nov 10, 2026 | Real public data |
| OMB performance measures, ADF&G Habitat (C486) | FY2025 averages: Fish Habitat 7.8 days, Special Area 13.5 days | Nov 10, 2026 | Real public data |
| OMB performance measures, DMLW (C3002) | Context for the bottleneck report (land use received and issued, backlog 223) | Nov 8, 2026 | Real public data |
| OPMP, Permitting Large Mine Projects in Alaska | Joint public notice for plan of operations, reclamation, waste management | Nov 10, 2026 | Real public data |
| DEC regulations via Internet Archive (dec.alaska.gov blocks automated clients) | 401, wastewater, drinking water and APDES clocks | Nov 10, 2026 | Real public data |
| US Census cartographic boundary (Alaska outline) | Statewide project map | Nov 8, 2026 | Real public data |
Authorizations and clocks
21 State authorizations| Authorization | Unit | Citation | Clock | Source |
|---|---|---|---|---|
| Land use permit | DNR Lands | AS 38.05.850; 11 AAC 96 | Published target: 30 days · Regional staff aim to finish adjudication within 30 days of a complete application | DMLW, how to apply |
| Tideland lease | DNR Lands | AS 38.05.070, .075; 11 AAC 58 | Published target: 365 days · 9 to 12 months after a complete application | DMLW Lands Section |
| Lease (lodge site) | DNR Lands | AS 38.05.070, .075; 11 AAC 58 | Published target: 365 days · 9 to 12 months after a complete application | DMLW Lands Section |
| Easement (access road) | DNR Lands | AS 38.05.850 | Published target: 240 days · 6 to 8 months after a complete application | DMLW Lands Section |
| APMA plan of operations (miscellaneous land use permit) | DNR Mining | 11 AAC 86.150; Application for Permits to Mine in Alaska | Working target: 60 days · No deadline; applications processed in the order received | DNR APMA application |
| Plan of operations approval | DNR Mining | 11 AAC 86.800 | Working target: 270 days · No decision deadline found | OPMP, Permitting Large Mine Projects |
| Reclamation plan approval | DNR Mining | AS 27.19.030; 11 AAC 97.300 | Law: 30 days · Decision within 30 days after a complete plan; DNR may extend by written notice | 11 AAC 97.300 |
| Millsite and tailings lease | DNR Mining | AS 38.05.255; 11 AAC 86.600 | Working target: 180 days · Steps in law; no decision deadline | AS 38.05.255 |
| Temporary water use authorization | DNR Water | AS 46.15.155; 11 AAC 93.210-.220 | Published target: 60 days · Apply 60 days before the water is needed | DNR TWUA page |
| Water right | DNR Water | AS 46.15; 11 AAC 93.035-.130 | Working target: 90 days · 15-day objection period; decision within 30 days of the last objection | AS 46.15.133 |
| Dam safety certificate to construct | DNR Water | AS 46.17.040; 11 AAC 93.171 | Working target: 180 days · Schedule set case by case; none fixed | DNR Dam Safety |
| APDES individual discharge permit | DEC Water | AS 46.03.100, .110; 18 AAC 83 | Working target: 210 days · No deadline for the draft or final permit | 18 AAC 83.110 |
| Clean Water Act 401 certification | DEC Water | 33 USC 1341; 18 AAC 15.130-.180 | Law: 30 days · Decision within 30 days of the federal agency's proposed action | 18 AAC 15.180(b) |
| Integrated waste management permit | DEC Water | AS 46.03.100(b)(5); 18 AAC 60.200-.270 | Working target: 180 days · No decision deadline found | 18 AAC 60.200 |
| Wastewater plan approval to construct | DEC Water | 18 AAC 72.511, .515 | Law: 30 days · Decision within 30 days after all information is received; not automatic approval | 18 AAC 72.225(a) |
| Drinking water approval to construct | DEC Environmental Health | 18 AAC 80.200-.230 | Law: 30 days · Decision within 30 days after all information is received; not automatic approval | 18 AAC 80.210(a) |
| Food service permit | DEC Environmental Health | 18 AAC 31 | Working target: 30 days · Apply 30 days before operation; no review deadline found | 18 AAC 31.010 |
| Solid waste general permit (remote camps and lodges) | DEC Environmental Health | 18 AAC 60 | Working target: 30 days · General permit for remote camps and lodges under 50 residents | 18 AAC 60.200 |
| Air quality minor permit | DEC Air | AS 46.14.170; 18 AAC 50.502-.542 | Law: 30 days · Minor permit within 30 days of complete or of comment close | AS 46.14.170(d) |
| Fish Habitat permit | ADF&G Habitat | AS 16.05.871, .841 | Published target: 28 days · Project review and permitting takes about 2 to 4 weeks | ADF&G Habitat FAQ |
| Special Area permit | ADF&G Habitat | AS 16.20.530; 5 AAC 95.420 | Published target: 28 days · About 2 to 4 weeks; FY2025 average 13.5 days | ADF&G Habitat FAQ |
Synthetic
Synthetic cases
- Every project, applicant, contact, address and email (50 projects: 3 flagship, 45 portfolio, 2 in intake).
- Every staff name and title; agencies, units and offices are real.
- Every date, pause, request, answer, public comment, permit number and file number.
- Special area boundaries: names are real, boxes are approximate.
- Working targets on steps with no published clock (labelled Working target on every step).
- Decision template wording and standard conditions without a citation.
Unconfirmed
- Whether a marine dock outside a catalogued stream mouth falls outside AS 16.05.871 (inference).
- Decision deadline for a DEC integrated waste management permit.
- DEC food service permit review deadline.
- Lodge generator thresholds for a DEC air minor permit (not screened).
- Corps Alaska District regional general permit list and default 401 period.
- Whether the Legislature funded the FY2027 LAS replacement request.