About the data

Mixed

Demo date Nov 9, 2026

Real sources

15 sources
SourceUsed forRetrievedData
ADF&G Anadromous Waters Catalog 2026, anadromous streams layer1,400 stream lines in nine areas (Kachemak Bay, Lake Creek and Yentna, Chatanika, Juneau, Ketchikan, Kodiak, Valdez, Sitka, Kenai): Fish Habitat screening and site mapsNov 10, 2026Real public data
ADF&G Habitat Section regional boundariesHabitat office phone and email on the home pageNov 10, 2026Real public data
DNR OpenData Land Permit or Lease polygonsExisting LAS cases checked at intake and drawn on site maps (cached in ak-las)Nov 8, 2026Real public data
DNR OpenData Easement polygonsExisting LAS easement cases at intake (cached in ak-las)Nov 8, 2026Real public data
DMLW land use permit process, fees, offices30-day permit aim, fees, land office addresses and phonesNov 8, 2026Real public data
DMLW Lands SectionLease 9 to 12 months, easement 6 to 8 monthsNov 10, 2026Real public data
AO 355 final reportLand use permit 14-day public noticeNov 10, 2026Real public data
Administrative Order 360Public status and timelines directionNov 10, 2026Real public data
Alaska Statutes and Administrative Code (akleg.gov)Every legal clock, notice period and citation on a stepNov 10, 2026Real public data
ADF&G Habitat permit FAQFish Habitat and Special Area 2 to 4 week targetNov 10, 2026Real public data
OMB performance measures, ADF&G Habitat (C486)FY2025 averages: Fish Habitat 7.8 days, Special Area 13.5 daysNov 10, 2026Real public data
OMB performance measures, DMLW (C3002)Context for the bottleneck report (land use received and issued, backlog 223)Nov 8, 2026Real public data
OPMP, Permitting Large Mine Projects in AlaskaJoint public notice for plan of operations, reclamation, waste managementNov 10, 2026Real public data
DEC regulations via Internet Archive (dec.alaska.gov blocks automated clients)401, wastewater, drinking water and APDES clocksNov 10, 2026Real public data
US Census cartographic boundary (Alaska outline)Statewide project mapNov 8, 2026Real public data

Authorizations and clocks

21 State authorizations
AuthorizationUnitCitationClockSource
Land use permitDNR LandsAS 38.05.850; 11 AAC 96Published target: 30 days · Regional staff aim to finish adjudication within 30 days of a complete applicationDMLW, how to apply
Tideland leaseDNR LandsAS 38.05.070, .075; 11 AAC 58Published target: 365 days · 9 to 12 months after a complete applicationDMLW Lands Section
Lease (lodge site)DNR LandsAS 38.05.070, .075; 11 AAC 58Published target: 365 days · 9 to 12 months after a complete applicationDMLW Lands Section
Easement (access road)DNR LandsAS 38.05.850Published target: 240 days · 6 to 8 months after a complete applicationDMLW Lands Section
APMA plan of operations (miscellaneous land use permit)DNR Mining11 AAC 86.150; Application for Permits to Mine in AlaskaWorking target: 60 days · No deadline; applications processed in the order receivedDNR APMA application
Plan of operations approvalDNR Mining11 AAC 86.800Working target: 270 days · No decision deadline foundOPMP, Permitting Large Mine Projects
Reclamation plan approvalDNR MiningAS 27.19.030; 11 AAC 97.300Law: 30 days · Decision within 30 days after a complete plan; DNR may extend by written notice11 AAC 97.300
Millsite and tailings leaseDNR MiningAS 38.05.255; 11 AAC 86.600Working target: 180 days · Steps in law; no decision deadlineAS 38.05.255
Temporary water use authorizationDNR WaterAS 46.15.155; 11 AAC 93.210-.220Published target: 60 days · Apply 60 days before the water is neededDNR TWUA page
Water rightDNR WaterAS 46.15; 11 AAC 93.035-.130Working target: 90 days · 15-day objection period; decision within 30 days of the last objectionAS 46.15.133
Dam safety certificate to constructDNR WaterAS 46.17.040; 11 AAC 93.171Working target: 180 days · Schedule set case by case; none fixedDNR Dam Safety
APDES individual discharge permitDEC WaterAS 46.03.100, .110; 18 AAC 83Working target: 210 days · No deadline for the draft or final permit18 AAC 83.110
Clean Water Act 401 certificationDEC Water33 USC 1341; 18 AAC 15.130-.180Law: 30 days · Decision within 30 days of the federal agency's proposed action18 AAC 15.180(b)
Integrated waste management permitDEC WaterAS 46.03.100(b)(5); 18 AAC 60.200-.270Working target: 180 days · No decision deadline found18 AAC 60.200
Wastewater plan approval to constructDEC Water18 AAC 72.511, .515Law: 30 days · Decision within 30 days after all information is received; not automatic approval18 AAC 72.225(a)
Drinking water approval to constructDEC Environmental Health18 AAC 80.200-.230Law: 30 days · Decision within 30 days after all information is received; not automatic approval18 AAC 80.210(a)
Food service permitDEC Environmental Health18 AAC 31Working target: 30 days · Apply 30 days before operation; no review deadline found18 AAC 31.010
Solid waste general permit (remote camps and lodges)DEC Environmental Health18 AAC 60Working target: 30 days · General permit for remote camps and lodges under 50 residents18 AAC 60.200
Air quality minor permitDEC AirAS 46.14.170; 18 AAC 50.502-.542Law: 30 days · Minor permit within 30 days of complete or of comment closeAS 46.14.170(d)
Fish Habitat permitADF&G HabitatAS 16.05.871, .841Published target: 28 days · Project review and permitting takes about 2 to 4 weeksADF&G Habitat FAQ
Special Area permitADF&G HabitatAS 16.20.530; 5 AAC 95.420Published target: 28 days · About 2 to 4 weeks; FY2025 average 13.5 daysADF&G Habitat FAQ

Synthetic

Synthetic cases
  • Every project, applicant, contact, address and email (50 projects: 3 flagship, 45 portfolio, 2 in intake).
  • Every staff name and title; agencies, units and offices are real.
  • Every date, pause, request, answer, public comment, permit number and file number.
  • Special area boundaries: names are real, boxes are approximate.
  • Working targets on steps with no published clock (labelled Working target on every step).
  • Decision template wording and standard conditions without a citation.

Unconfirmed

  • Whether a marine dock outside a catalogued stream mouth falls outside AS 16.05.871 (inference).
  • Decision deadline for a DEC integrated waste management permit.
  • DEC food service permit review deadline.
  • Lodge generator thresholds for a DEC air minor permit (not screened).
  • Corps Alaska District regional general permit list and default 401 period.
  • Whether the Legislature funded the FY2027 LAS replacement request.